Singapore · 2020
Keppel Marina East Desalination Plant
Cable support layouts designed in AVEVA PDMS, calculated, load-tested and supplied: cable ladder on channel support racks
Keppel Marina East Desalination Plant is Singapore’s first large-scale dual-mode desalination plant. It treats seawater, or freshwater from Marina Reservoir in wet weather, in treatment halls that sit beneath a public green roof. Array Metal engineered, manufactured and delivered the cable support system for the plant: cable ladder carried on channel-framed racks, mounted from the slab, the ceiling, structural steel and the walls.
The support layouts were designed in AVEVA PDMS, within the plant’s 3D model. Ladder routes were set out around the pipework, ducts and equipment and checked against the other trades, and the bill of materials was taken from the same model, so what was fabricated matched what was drawn.
The job ran from March to October 2018, from kick-off to phased delivery to site. Four of its stages are shown below.
- Location
- Singapore
- Year
- 2020
- Sector
- Water Treatment
Project stages
Every support type was agreed, calculated and proven before production, and every delivery was checked before it left our plant.
- 01Technical conceptual meetingSupport types and ladder routes agreed in the 3D model
- 02PE endorsementRack design calculation endorsed by a Singapore Professional Engineer
- 03Pre-delivery inspectionEvery outgoing delivery checked at our plant
- 04Site installationSlab, ceiling, steel and wall-mounted racks installed on site
01
Technical conceptual meeting
After kick-off, a technical conceptual meeting with the client set the support types for each area: ceiling-mounted, structural-steel-mounted, slab-mounted and wall-mounted.
The layouts were then designed in AVEVA PDMS, within the plant’s 3D model, and submitted as drawings for technical clarification. The bill of materials was taken from the same model.
02
PE endorsement
The framing racks were checked with a static load simulation, and the rack design calculation was endorsed by a Singapore Professional Engineer.
Around it, sample frames were set up on site for the client’s mock-up buy-off, and a sample rack was load-tested at our plant under the client’s witness before manufacturing was cleared.
03
Pre-delivery inspection
Each delivery was inspected at our plant before it left for Singapore. Every member was marked with its rack reference, so the installers could match each part to the layout, then strapped and wrapped on pallets.
04
Site installation
Deliveries were phased to follow construction on site. Slab-mounted racks went in first on the open floors, and ceiling-mounted ladder was hung from boom lifts in the treatment halls.