Singapore · 2020

Keppel Marina East Desalination Plant

Cable support layouts designed in AVEVA PDMS, calculated, load-tested and supplied: cable ladder on channel support racks

Keppel Marina East Desalination Plant is Singapore’s first large-scale dual-mode desalination plant. It treats seawater, or freshwater from Marina Reservoir in wet weather, in treatment halls that sit beneath a public green roof. Array Metal engineered, manufactured and delivered the cable support system for the plant: cable ladder carried on channel-framed racks, mounted from the slab, the ceiling, structural steel and the walls.

The support layouts were designed in AVEVA PDMS, within the plant’s 3D model. Ladder routes were set out around the pipework, ducts and equipment and checked against the other trades, and the bill of materials was taken from the same model, so what was fabricated matched what was drawn.

The job ran from March to October 2018, from kick-off to phased delivery to site. Four of its stages are shown below.

Location
Singapore
Year
2020
Sector
Water Treatment

Project stages

Every support type was agreed, calculated and proven before production, and every delivery was checked before it left our plant.

01

Technical conceptual meeting

After kick-off, a technical conceptual meeting with the client set the support types for each area: ceiling-mounted, structural-steel-mounted, slab-mounted and wall-mounted.

The layouts were then designed in AVEVA PDMS, within the plant’s 3D model, and submitted as drawings for technical clarification. The bill of materials was taken from the same model.

A ladder route turning around the large-bore pipework, as modelled.
Stacked ladder tiers on support frames above the pumps, as modelled. The bill of materials came from the same model.

02

PE endorsement

The framing racks were checked with a static load simulation, and the rack design calculation was endorsed by a Singapore Professional Engineer.

Around it, sample frames were set up on site for the client’s mock-up buy-off, and a sample rack was load-tested at our plant under the client’s witness before manufacturing was cleared.

Mock-up buy-off: sample frames set up on site for the client to approve before production.
Witnessed load test at the Array Metal plant: a sample rack loaded with cable ladder.

03

Pre-delivery inspection

Each delivery was inspected at our plant before it left for Singapore. Every member was marked with its rack reference, so the installers could match each part to the layout, then strapped and wrapped on pallets.

Members marked with their rack reference, checked before dispatch.

04

Site installation

Deliveries were phased to follow construction on site. Slab-mounted racks went in first on the open floors, and ceiling-mounted ladder was hung from boom lifts in the treatment halls.

Slab-mounted racks going in during construction.
Rows of slab-mounted racks with the ladder laid in.
Ceiling-mounted ladder installed from a boom lift.
A long rack run along the wall during fit-out.